Treatment Plant Engineering

Big Creek AWTP Expansion

Managed a $230M wastewater treatment plant expansion, 36 MGD to 54 MGD, for EPA/EPD compliance.

Scope of work

What we delivered.

  • Oversaw headworks, aeration basins, membrane bioreactors, chemical storage & dewatering systems
  • Full CDA administration: submittals, RFIs, RFPs, change orders & progress payments
  • Stakeholder coordination via Management Information System throughout construction
ProjectTreatment Plant Engineering
Client
Fulton County
Role
Project Manager
Contract
CM Contract T&M $2.3M · Total Project $230M

Advance Engineering & Construction

Have a similar program?

Tell us about the work. We bring design, construction management, and federal compliance to every water project.